Annual requirement is 7800 units; consumption per week is 150 units. Unit price 5, order cost 10 per order. Carrying cost 1 per unit and lead time is 3 week, The Economic order quantity would be.

Question:
Annual requirement is 7800 units; consumption per week is 150 units. Unit price 5, order cost 10 per order. Carrying cost 1 per unit and lead time is 3 week, The Economic order quantity would be.

1.395 units

2.300 units

3.250 units

4.150 units