A can finish a work in 7 days B in 14 days and C in 28 days. B and C start working and are forced to leave the work after 2 days. The number of days taken by A to finish the remaining work is
1.8.5 days
2.10 days
3.5.5 days
4.15.5 days
Answer:3
Posted Date:-2021-09-20 02:50:13