A can finish a work in 20 days B can do the same work in 10 days. After A has worked for 5 days B joins A in how many days the remaining work will be finished.

Question:
A can finish a work in 20 days B can do the same work in 10 days. After A has worked for 5 days B joins A in how many days the remaining work will be finished.

1.15 days

2.8 days

3.5 days

4.7 days