A can do a work in 40 days and B can do it is 25 days. A worked at it for 8 days. In how many days B can finish the remaining work.

Question:
A can do a work in 40 days and B can do it is 25 days. A worked at it for 8 days. In how many days B can finish the remaining work.

1.8 days

2.20 days

3.16 days

4.12 days