A can do a work in 40 days and B can do it is 25 days. A worked at it for 8 days. In how many days B can finish the remaining work.
1.8 days
2.20 days
3.16 days
4.12 days
Answer:2
Posted Date:-2021-09-20 02:50:13
More MCQS Questions and answers
Search
R4R Team
R4Rin Top Tutorials are Core Java,Hibernate ,Spring,Sturts.The content on R4R.in website is done by expert team not only with the help of books but along with the strong professional knowledge in all context like coding,designing, marketing,etc!