16 men can finish two fifth of the work in 4 days. The number of additional men required to finish the remaining work in 2 more days will be

Question:
16 men can finish two fifth of the work in 4 days. The number of additional men required to finish the remaining work in 2 more days will be

1.24 men

2.0 men

3.30 men

4.39 men

Posted Date:-2021-09-20 02:50:13