A can finish a work in 24 days B can finish the same work in 36 days. If they work together and finish it then out of total wages of Rs. 500 A will get
A can finish a work in 24 days B can finish the same work in 36 days. If they work together and finish it then out of total wages of Rs. 500 A will get
1.Rs. 220
2.Rs. 200
3.Rs. 300
4.Rs. 360
Answer:3