In a object oriented software design, ‘Inheritance’ is a kind of...................
1.relationship
2.module
3.testing
4.optimization
Posted Date:-2022-05-31 22:40:08
In software project planning, work Breakdown structure must be .................
1.A graph
2.A tree
3.A Euler’s graph
4.None of the above
Posted Date:-2022-05-31 22:43:10
System development cost estimation with use-cases is problematic because:
1.of paucity of examples
2.the data can be totally incorrect
3.the expertise and resource available are not used
4.the problem is being over simplified
Posted Date:-2022-05-31 22:07:32
The main objective of designing various modules of a software system is:
1.To decrease the cohesion and to increase the coupling
2.To increase the cohesion and to decrease the coupling
3.To increase the coupling only
4.To increase the cohesion only
Posted Date:-2022-05-31 23:02:18
Three essential components of a software project plan are:
1.Team structure, Quality assurance plans, Cost estimation
2.Cost estimation, Time estimation, Quality assurance plan
3.Cost estimation, Time estimation, Personnel estimation
4.Cost estimation, Personnel estimation, Team structure
Posted Date:-2022-05-31 23:03:46
Which possibility among the following is invalid in case of a Data Flow Diagram ?
1.A process having in-bound data flows more than out-bound data flows
2.A data flow between two processes
3.A data flow between two data stores
4.A data store having more than one in-bound data flows
Posted Date:-2022-05-31 22:20:17
A black hole in a DFD is a:
1.A data store with no inbound flows
2.A data store with only in bound flows
3.A data store with more than one in bound flow
4.None of These
Posted Date:-2022-05-31 22:54:28
A major defect in water fall model in software development is that:
1.the documentation is difficult
2.a blunder at any stage can be disastrous
3. a trial version is available only at the end of the project
4. the maintenance of the software is difficult
Posted Date:-2022-05-31 22:03:49
Abstraction’ is......................step of Attribute in a software design.
1.First
2.Final
3.Last
4.Middle
Posted Date:-2022-05-31 22:41:57
An error message produced by an interactive system should have:
1.always the error code
2. the list of mistakes done by the user displayed
3. a non-judgemental approach
4.the past records of the occurrence of the same mistake
Posted Date:-2022-05-31 22:06:26
Black Box testing is done
1.to show that s/w is operational at its interfaces i.e. input and output.
2.to examine internal details of code.
3.at client side
4.None of the above
Posted Date:-2022-05-31 04:47:17
Capability Maturity Model is meant for:
1.Product
2.Process
3.Product and Process
4.None of the above
Posted Date:-2022-05-31 21:48:52
COCOMO model is used for:
1.product quality estimation
2.product complexity estimation
3.product cost estimation
4. all of the above
Posted Date:-2022-05-31 21:55:48
Difference between flow-chart and data-flow diagram is:
1.there is no difference
2. usage in high level design and low level design
3.control flow and data flow
4.used in application programs and system programs
Posted Date:-2022-05-31 22:12:14
Function point metric of a software also depends on the:
1. number of function needed
2. number of final users of the software
3.number of external inputs and outputs
4. time required for one set of output from a set of input data
Posted Date:-2022-05-31 22:04:58
In a good software design, ................ coupling is desirable between modules.
1.Highest
2.Lowest
3.Internal
4.External
Posted Date:-2022-05-31 22:45:32
In clean room software engineering:
1.only eco-friendly hardware is used.
2.only hired facilities are used for development.
3.correctness of the code is verified before testing.
4.implementation is done only after ensuring correctness.
Posted Date:-2022-05-31 22:02:40
In software cost estimation, base estimation is related to:
1. cost of similar projects already completed
2.cost of the base model of the present project.
3. cost of the project with the base minimum profit
4. cost of the project under ideal situations
Posted Date:-2022-05-31 22:01:09
In Software Metrics, McCABE’s cyclomatic number is given by following formula:
1.c=e-n+2p
2. c=e-n-2p
3. c=e+n+2p
4.c=e-n*2p
Posted Date:-2022-05-31 22:44:36
In the light of software engineering software consists of:
1.Programs b.
2.Data
3.Documentation
4. All of the above
Posted Date:-2022-05-31 21:49:52
Match the following: (a) Unit test (i) Requirements (b) System test (ii) Design (c) Validation test (iii) Code (d) Integration test (iv) System Engineering Which of the following is true? (a) (b) (c) (d)
1.(ii) (iii) (iv) (i)
2. (i) (ii) (iv) (iii)
3. (iii) (iv) (i) (ii)
4.None of the above
Posted Date:-2022-05-31 22:16:55
n software development, value adjustment factors include the following among others:
1.the criticality of the performance and reusability of the code.
2.number of lines of code in the software.
3.number of technical manpower and hardware costs.
4.time period available and the level of user friendliness.
Posted Date:-2022-05-31 21:58:48
Problems with waterfall model are: 1. Real projects rarely follow this model proposes 2. It is often difficult for the customer 3. Working model is available only in the end 4. Developers are delayed unnecessarily
1.1 and 4 only
2. 2 and 3 only
3.1, 2 and 3 only
4.1, 2, 3 and 4
Posted Date:-2022-05-31 22:17:59
Reliability of software is dependent on:
1.Number of errors present in software
2. Documentation
3. Testing suties
4.Development Processes
Posted Date:-2022-05-31 23:04:50
Reliability of software is directly dependent on:
1.quality of the design
2. number of errors present
3. software engineer’s experience
4.user requirement
Posted Date:-2022-05-31 22:41:04
Reverse engineering is the process which deals with:
1.Size measurement
2.Cost measurement
3.Design recovery
4.All of the above
Posted Date:-2022-05-31 21:52:46
Sliding window concept of software project management is:
1.Preparation of comprehensible plan
2.Ad-hoc planning
3. Preparation of the various stages of development
4.Requirement analysis
Posted Date:-2022-05-31 22:53:35
Software Cost Performance index (CPI) is given by: (Where: BCWP stands for Budgeted Cost of Work Performed BCWS stands for Budget Cost of Work Scheduled ACWP stands for Actual Cost of Work Performed)
1.BCWP/ACWP
2.BCWP−ACWP
3.BCWP−BCWS
4.None of the above
Posted Date:-2022-05-31 22:30:49
Software Quality Assurance(SQA) encompasses:
1.verification
2.validation
3. both verification and validation
4.None of the above
Posted Date:-2022-05-31 21:53:51
Software Risk estimation involves following two tasks:
1.risk magnitude and risk impact
2. risk probability and risk impact
3. risk maintenance and risk impact
4. risk development and risk impact
Posted Date:-2022-05-31 22:34:14
Successive layer of design in software using bottom-up design is called:
1.Layer of Refinement
2. Layer of Construction
3.Layer of abstraction
4.None of the above
Posted Date:-2022-05-31 22:52:12
System Development Life-cycle has following stages: (I) Requirement analysis (II) Coding (III) Design (IV) Testing Which option describes the correct sequence of stages?
1.III, I, IV, II
2.II, III, I, IV
3.I, III, IV, II
4.None of the above
Posted Date:-2022-05-31 22:58:51
System study yields the following:
1.System study yields the following:
2.Requirement specifications
3.Prevailing process description
4.Data source identification
Posted Date:-2022-05-31 22:46:37
The approach to software testing is to design test cases to:
1.break the software
2.understand the software
3. analyze the design of sub processes in the software
4.analyze the output of the software
Posted Date:-2022-05-31 22:08:55
The capability maturity model (err) defines 5 levels: (a) Level 1 (i) Managed (b) Level 2 (ii) Defined (c) Level 3 (iii) Repeatable (d) Level 4 (iv) Initial (e) Level 5 (v) Optimized correct matching is: a b c d e
1.(i) (ii) (iii) (iv) (v)
2. (iv) (iii) (ii) (i) (v)
3. (v) (i) (iii) (ii) (iv)
4. (v) (ii) (i) (iii) (iv)
Posted Date:-2022-05-31 22:55:29
The COCOMO model is used for .............
1.software design
2.software cost estimation
3. software cost approximation
4. software analysis
Posted Date:-2022-05-31 22:47:33
The lower degree of cohesion is:
1.logical cohesion
2.coincidental cohesion
3. procedural cohesion
4.communicational cohesion
Posted Date:-2022-05-31 22:49:38
The reliability of the software is directly dependent upon:
1.Quality of the design
2.Programmer’s experience
3. Number of error
4.Set of user requirements
Posted Date:-2022-05-31 22:50:54
The testing of software against SRS is called:
1.Acceptance testing
2. Integration testing
3.Regression testing
4.Series testing
Posted Date:-2022-05-31 22:48:30
Water fall model for software development is:
1.a top down approach
2.a bottom up approach
3. a sequential approach
4. a consequential approach
Posted Date:-2022-05-31 21:56:45
Which level is called as “defined” in capability maturity model?
1.level 0
2.level 3
3. level 4
4.level 1
Posted Date:-2022-05-31 21:54:46
Which of the following combination is preferred with respect to cohesion and coupling?
1.low and low
2. low and high
3.high and low
4.high and high
Posted Date:-2022-05-31 22:10:21
Which of the following is used for test data generation?
1.White box
2.Black box
3. Boundary-value analysis
4.All of the above
Posted Date:-2022-05-31 21:51:40
Which of the following tools is not required during system analysis phase of system development life cycle?
1.Case tool
2.RAD tool
3.Reverse engineering
4.None of These
Posted Date:-2022-05-31 22:21:09
Which one is measure of software complexity ?
1.Number of lines of code (LOC)
2. Number of man years
3. Number of function points (FP)
4.None of the above
Posted Date:-2022-05-31 22:59:57
Which one of the following is a object-oriented approaches:
1.The Booch method
2.The Rumbaugh method
3.The Coad and Yomdon method
4.All of the above
Posted Date:-2022-05-31 22:19:12
Which one of the following is not a software process model ?
1.Linear sequential model
2.Prototyping model
3.The spiral model
4.COCOMO model
Posted Date:-2022-05-31 22:56:43
Which one of the following ISO standard is used for software process?
1.ISO 9000
2.ISO 9001
3. ISO 9003
4. ISO 9000-3
Posted Date:-2022-05-31 21:50:49
Which type of coupling is least preferred ?
1.Content coupling
2.Data coupling
3. Control coupling
4.Common coupling
Posted Date:-2022-05-31 23:01:05
While designing the user interface, one should:
1.use as many short cuts as possible.
2.use as many defaults as possible.
3.use as many visual layouts as possible.
4. reduce the demand on short-term memory.
Posted Date:-2022-05-31 21:59:54